Columbus Consolidated Government Columbus, GA
|
Pine Grove Municipal Solid Waste Landfill Phase 4 - Cells 4A
|
$0
|
2/9/2012
|
2/29/2012
|
|
Request Info: | |
|
|
Notes: | | The project will consist of clearing and grubbing: earthwork (cut/fill) to subbase elevations; placement of 24-inch thick liner base with permeability not to exceed 1x10-7 cm/sec., or GCL with a 24-inch thick base liner with a permeability not to exceed 1x10-5 cm/sec. and placement of either a 24-inch thick leachate collection layer with a permeability no less than 1 x 10-2 cm/sec. or placement of geonet and 24 inches of a soil layer with no specified permeability; a 60 mil HDPE geomembrane liner over 16.1 acres; the construction of 1,300 feet of 24-foot gravel access road; installation of erosion control devices; installation of a stormwater protection layer; installation of underdrain and leachate collection, and force main piping. THE CITY WILL ONLY CONSIDER BIDS FROM PRE-QUALIFIED CONTRACTORS.
|
|